title: Arc flash studies in 62 power plants and assessment tools
date: 2021-04-05T11:11:00-04:00
author: jessica napert
canonical_url: "https://www.bbaconsultants.com/es-cl/projects/arc-flash-studies-in-62-power-plants-and-assessment-tools"
section: Projects
---
Hydro-Québec Production wanted to perform an arc flash hazard assessment in electrical facilities (AC and DC) for 62 power plants. This project was part of an initiative to ensure the safety of personnel working near electrical facilities and to comply with ULC-S801 and CSA Z462 standards.

 

- Región Este de Canadá
- Cliente  Hydro-Québec
 
 

 

 

   1. ## Our experts' solutions
    
    Because Hydro-Québec requires a high degree of accuracy, BBA worked closely with the client to produce a calculation method that included the decay effect of generator sets during a fault.
    
    BBA used ETAP software for this mandate, so, as a result, our experts trained Hydro-Québec staff to use it.
    
    
    - Proposed a methodology to assess the incident energy that included the fault current decay of generator sets.
    - Performed a short-circuit study and determined protection settings on high-, medium- and low-voltage facilities to assess arc duration.
    - Performed an arc flash hazard analysis with existing protection settings.
    - Developed risk analysis tables showing the settings prescribed by the standards for each work location (limit perimeter, work distances and thermal resistance of personal protective equipment).
 
        

  

  

 

 1. > In addition to bolstering the safety of Hydro-Québec Production workers during this mandate, we had the opportunity to train them and provide technical support to study engineers to ensure their autonomy in assessing arc flash hazards in electrical facilities.
    
     Joël Sourceaux, Expert, Power Systems Studies, BBA
 
   - [  12 ago 2026 
    
     Four mistakes that can harm the future performance of industrial assets 
    
     
    
     
    
    
    - ![Caroline provost](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/208557/Caroline-provost.webp)   
        
         Caroline Provost P.Eng.
        
        Director, Operational Strategy Implementation
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/four-mistakes-that-can-harm-the-future-performance-of-industrial-assets "Four mistakes that can harm the future performance of industrial assets")
- [  29 jul 2026 
    
     Sachin Jari appointed Principal Director &amp; Head of Commercial Strategy and Business Development 
    
     
    
     
    
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/news/sachin-jari-appointed-principal-director-head-of-commercial-strategy-and-business-development "Sachin Jari appointed Principal Director & Head of Commercial Strategy and Business Development")
- [  27 jul 2026 Minería y metalurgia  
    
     
    
     Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo 
    
     
    
     
    
    
    - ![Geraldine Cosset](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/206707/Geraldine-Cosset.webp)
    - ![Jared Purdy](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/212424/Jared-Purdy.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/las-decisiones-sobre-relaves-definen-desempeno-mina-a-largo-plazo "Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo")
- [  02 jul 2026 Minería y metalurgia  
    
     
    
     Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales 
    
     
    
     
    
    
    - ![Charles Blais](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211197/Charles-Blais.webp)
    - ![Juan Pablo Vergara](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211266/Juan-Pablo-Vergara.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/python-una-herramienta-clave-para-analisis-datos-en-procesamiento-minerales "Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales")
 
 

       

 

 

   

 Veamos lo  
que podemos  
hacer juntos [ Póngase en contacto con nosotros    

 ](https://www.bbaconsultants.com/es-cl/p%C3%B3ngase-en-contacto-con-nosotros) 

 

   

 1. ## Our experts' solutions
    
    Because Hydro-Québec requires a high degree of accuracy, BBA worked closely with the client to produce a calculation method that included the decay effect of generator sets during a fault.
    
    BBA used ETAP software for this mandate, so, as a result, our experts trained Hydro-Québec staff to use it.
    
    
    - Proposed a methodology to assess the incident energy that included the fault current decay of generator sets.
    - Performed a short-circuit study and determined protection settings on high-, medium- and low-voltage facilities to assess arc duration.
    - Performed an arc flash hazard analysis with existing protection settings.
    - Developed risk analysis tables showing the settings prescribed by the standards for each work location (limit perimeter, work distances and thermal resistance of personal protective equipment).