Today, rigorous witnessing of factory acceptance tests (FATs) performed by an expert who is directly involved in the project engineering process is proving to be key when carrying out detailed engineering projects. On the one hand, it prevents disruptions when completing an engineering project and, on the other hand, minimizes the risk of undue delays during plant commissioning and start-up. It also prevents significant production losses in case critical equipment is unexpectedly damaged in the initial years of operation.

 

1. **Experience shows that, in general, intensifying FATs helps:**
    
    
    - Reduce the risk of litigation following project execution.
    - Improve the insurability of a plant, knowing that the risks of premature damage are much lower when the FATs have been performed rigorously.
    
    However, FATs are often sacrificed in favour of shortening the schedule and for financial considerations.
    
    This document will demonstrate that properly following project steps to optimize nominal life expectancy is more beneficial than accelerating the process to save money or to shorten the schedule, which would negatively affect process operation.
 
This content is for general information purposes only. All rights reserved ©BBA

 

    1. ![Maurice Brisson canva](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/204414/Maurice-Brisson-canva.webp)   
    
     Maurice Brisson, Ing., M.C.A.
    
    Experto Consultor Senior, Planificación de Sistemas Eléctricos
    
         Leer bio    Maurice cuenta con más de 50 años de experiencia en sistemas de media y alta tensión, combinando experiencia técnica, liderazgo y visión estratégica para el suministro eléctrico de proyectos industriales, instalaciones de energía renovable y redes complejas de transmisión y distribución.
    
    **Áreas de especialización**
    
    
    - Estudios tecnoeconómicos y desarrollo de redes eléctricas
    - Protección, compensación reactiva y filtrado armónico para procesos industriales
    - Planificación y análisis de redes de transmisión y distribución
    - Diagnóstico, resolución de problemas y diseño de diagramas unifilares
    
    **Principales logros**
    
    Proyectos que incluyen estudios, optimización y rehabilitación de subestaciones de hasta 345 kV para complejos industriales y parques renovables de 40–350 MW, incluyendo planificación y evaluación del desempeño de sistemas industriales y renovables complejos.
    
    **Enfoque y valor añadido**
    
    Maurice aplica un enfoque riguroso y pragmático, asegurando decisiones e inversiones mientras apoya la transición energética mediante proyectos robustos y de alto desempeño.
 
 

       

  

  

 

     - [  17 ago 2026 
    
     Structural engineering early phase: unlocking value through early decisions 
    
     
    
     
    
    
    - ![Nicolas Samson](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/197852/Nicolas-Samson.webp)   
        
         Nicolas Samson, P.Eng.
        
        Senior Engineer, Structural
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/structural-engineering-early-phase-unlocking-value-through-early-decisions "Structural engineering early phase: unlocking value through early decisions")
- [  12 ago 2026 
    
     Four mistakes that can harm the future performance of industrial assets 
    
     
    
     
    
    
    - ![Caroline provost](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/208557/Caroline-provost.webp)   
        
         Caroline Provost P.Eng.
        
        Director, Operational Strategy Implementation
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/four-mistakes-that-can-harm-the-future-performance-of-industrial-assets "Four mistakes that can harm the future performance of industrial assets")
- [  27 jul 2026 Minería y metalurgia  
    
     
    
     Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo 
    
     
    
     
    
    
    - ![Geraldine Cosset](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/206707/Geraldine-Cosset.webp)
    - ![Jared Purdy](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/212424/Jared-Purdy.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/las-decisiones-sobre-relaves-definen-desempeno-mina-a-largo-plazo "Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo")
- [  02 jul 2026 Minería y metalurgia  
    
     
    
     Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales 
    
     
    
     
    
    
    - ![Charles Blais](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211197/Charles-Blais.webp)
    - ![Juan Pablo Vergara](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211266/Juan-Pablo-Vergara.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/python-una-herramienta-clave-para-analisis-datos-en-procesamiento-minerales "Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales")
 
 

       

 

 [ Ver todo 

 ](https://www.bbaconsultants.com/es-cl/perspectivas "Ir a la página del listado de Publications") 

 

   

 Pensemos  
más [ Póngase en contacto con nosotros    

 ](https://www.bbaconsultants.com/es-cl/p%C3%B3ngase-en-contacto-con-nosotros) 

 

   

  Today, rigorous witnessing of factory acceptance tests (FATs) performed by an expert who is directly involved in the project engineering process is proving to be key when carrying out detailed engineering projects. On the one hand, it prevents disruptions when completing an engineering project and, on the other hand, minimizes the risk of undue delays during plant commissioning and start-up. It also prevents significant production losses in case critical equipment is unexpectedly damaged in the initial years of operation.

 

1. **Experience shows that, in general, intensifying FATs helps:**
    
    
    - Reduce the risk of litigation following project execution.
    - Improve the insurability of a plant, knowing that the risks of premature damage are much lower when the FATs have been performed rigorously.
    
    However, FATs are often sacrificed in favour of shortening the schedule and for financial considerations.
    
    This document will demonstrate that properly following project steps to optimize nominal life expectancy is more beneficial than accelerating the process to save money or to shorten the schedule, which would negatively affect process operation.
 