title: "Detailed engineering and commissioning of TransAlta's New Richmond wind farm"
date: 2021-04-27T14:49:00-04:00
author: jessica napert
canonical_url: "https://www.bbaconsultants.com/es-cl/section-projects/detailed-engineering-and-commissioning-of-transaltas-new-richmond-wind-farm"
section: Projects
---
TransAlta is recognized for its active participation in designing renewable energy projects across Canada. For the New Richmond project, the company had to commit to extremely ambitious construction and interconnection schedules to meet Hydro-Québec requirements. What was a stake? Powering Québec homes with wind-generated electricity.

 

- Región Este de Canadá
- Cliente  Venterre NRG (wholly owned by TransAlta Corporation)
 
 

 

 

   1. ## Our experts' solutions
    
    The team came together quickly and developed an innovative delivery strategy enabling the paralleling of design and procurement activities while optimizing prefabrication and minimizing rework. Results spoke for themselves, a project energized as planned that now displays one of the highest facility availability rate in the industry.
    
    The mandate was executed respecting a schedule compressed by five months for the electrical and civil design along major procurement activities.
    
    
    - Interconnection and electrical studies
    - Detailed engineering – civil, electrical and automation
    - Compliance with the IEC 61850 standard
    - Design and implementation of the SCADA system
    - Construction supervision of civil and electrical work
    - Testing and energization of all systems
 
        

  

  

 

 1. > The BBA team was able to bond seamlessly with the TransAlta team and was instrumental in fast tracking our project’s acceptance by Hydro-Québec for interconnection. BBA experts also brought hands-on expertise and were by our side, from design to energization.
    
     Julie Turgeon, Project Manager, TransAlta
2. - 33 E82, 2 MW and 2.3 MW wind turbines
    - 67.8 MW Wind farm totalling 67.8 MW
    - 230kV Wind farm connected to the Hydro-Québec 230kV grid
    - 11,000 Powering 11,000 Homes
    - Highest facility availability rate of its fleet
 
   - [  12 ago 2026 
    
     Four mistakes that can harm the future performance of industrial assets 
    
     
    
     
    
    
    - ![Caroline provost](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/208557/Caroline-provost.webp)   
        
         Caroline Provost P.Eng.
        
        Director, Operational Strategy Implementation
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/four-mistakes-that-can-harm-the-future-performance-of-industrial-assets "Four mistakes that can harm the future performance of industrial assets")
- [  29 jul 2026 
    
     Sachin Jari appointed Principal Director &amp; Head of Commercial Strategy and Business Development 
    
     
    
     
    
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/news/sachin-jari-appointed-principal-director-head-of-commercial-strategy-and-business-development "Sachin Jari appointed Principal Director & Head of Commercial Strategy and Business Development")
- [  27 jul 2026 Minería y metalurgia  
    
     
    
     Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo 
    
     
    
     
    
    
    - ![Geraldine Cosset](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/206707/Geraldine-Cosset.webp)
    - ![Jared Purdy](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/212424/Jared-Purdy.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/las-decisiones-sobre-relaves-definen-desempeno-mina-a-largo-plazo "Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo")
- [  02 jul 2026 Minería y metalurgia  
    
     
    
     Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales 
    
     
    
     
    
    
    - ![Charles Blais](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211197/Charles-Blais.webp)
    - ![Juan Pablo Vergara](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211266/Juan-Pablo-Vergara.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/python-una-herramienta-clave-para-analisis-datos-en-procesamiento-minerales "Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales")
 
 

       

 

 

   

 Veamos lo  
que podemos  
hacer juntos [ Póngase en contacto con nosotros    

 ](https://www.bbaconsultants.com/es-cl/p%C3%B3ngase-en-contacto-con-nosotros) 

 

   

 1. ## Our experts' solutions
    
    The team came together quickly and developed an innovative delivery strategy enabling the paralleling of design and procurement activities while optimizing prefabrication and minimizing rework. Results spoke for themselves, a project energized as planned that now displays one of the highest facility availability rate in the industry.
    
    The mandate was executed respecting a schedule compressed by five months for the electrical and civil design along major procurement activities.
    
    
    - Interconnection and electrical studies
    - Detailed engineering – civil, electrical and automation
    - Compliance with the IEC 61850 standard
    - Design and implementation of the SCADA system
    - Construction supervision of civil and electrical work
    - Testing and energization of all systems