Our experts' solutions
The project included installing new equipment, such as a 13.8 kV switch, a 13.8 kV/600 V transformer, a 4,000 A cable conduit and a 600 V switchgear. The BBA team was involved in every step, from preliminary studies, to determine the project concept, to design, detailed engineering and commissioning. All equipment had to be installed and pre-tested before the annual shutdown of plant operations. As a result, BBA had barely two nights to transfer the critical load of the two oil transformers to the new transformer.
- Developed a design that met client needs and drafted technical specifications and tender documents
- Performed detailed engineering, including civil engineering plans for the new outdoor transformer concrete slab, electrical plans and the contractor scope of work
- Revised and approved manufacturer drawings
- Reviewed protection settings to reduce exposure levels in the event of a failure that would generate an electric arc
- Performed onsite pre-operational verifications and commissioning