Henvey Inlet First Nation (HIFN), a community with 200 on-reserve residents located some 90 kilometres south of Sudbury, sought to build a wind farm that would turn strong gusts into clean energy. Their vision was to own and operate a facility that would support the Band’s future development by providing emission-free electricity and sustainable revenues from the sale of power to the province. However, the HIFN community still needed to be convinced that the development would not come at the expense of the biodiversity and traditional sites located within their Reserve.

 Premios y reconocimientos- OEPA Awards (ACEC Ontario)
 
 

- Región Centro de Canadá
- Clientes  Nigig Power Corporation , Pattern Canada , Henvey Inlet First Nation
- [ Caso práctico    
    
     ](https://www.assets.bbaconsultants.com/bba-production-assets/production/documents/pdf/BBA_Case-Study_Henvey_Inlet_Wind_Project_EN_2022-11-07-155158_oknh.pdf "Descargar el PDF de nuestro caso práctico")
 
 

 

 

   1. ## Our experts' solutions
    
    BBA’s engineers were tasked with designing and commissioning a facility that would meet all safety criteria while remaining cost-effective and environmentally responsible, two essential project targets
    
    Our experts faced many challenges: high ground resistivity, restricted or no access areas, wildlife, record snowfall and an iterative overnight design process.
    
    BBA’s rigorous approach to electrical design, project management and commissioning contributed directly to the project’s timely delivery. BBA had to plan site work in advance and tailor its designs to ensure minimal disturbance of sensitive areas. More specifically, we made a tremendous effort to minimize the width of cable trenches and ensure that wind turbine grounding grids would not encroach on environmentally restricted areas.
    
    As expected, many geographical issues—such as the presence of large boulders and a high water table—became evident during the trench-blasting and cable-laying phase. So, our team was forced to produce new construction designs in fewer than 24 hours to prevent costly delays and ensure phase completion. We later performed the commissioning in the winter, despite harsh climate conditions, to keep the project on schedule.
    
    Iterations were also needed to design the grounding grids for the two substations and 87 wind turbines. While granite bedrock is an excellent material for anchoring wind turbines, it is a poor electrical conductor and therefore complicates the grounding of structures.
    
    The result: the largest single-phase wind project in Ontario, as well as the largest First Nation wind partnership project in Canada. The wind farm is composed of two separate facilities, one on each side of an inlet that stretches from Lake Huron into Henvey Inlet Reserve No. 2.
 
        

  

  

 

 1. > Now that construction is complete, we can begin to look forward to economic independence as a community. Our youth will see an even brighter future from expanding health and education services along with increased infrastructure.
    
     Greg Newton, CEO of Nigig Power Corporation
2. - 300 mW of wind energy
    - 110 km of 34.5 kV buried collectors
    - Two 230 kV substations
    - 87 wind turbines
    - 20,000 hectare site
 
   - [  29 jul 2026 
    
     Sachin Jari appointed Principal Director &amp; Head of Commercial Strategy and Business Development 
    
     
    
     
    
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/news/sachin-jari-appointed-principal-director-head-of-commercial-strategy-and-business-development "Sachin Jari appointed Principal Director & Head of Commercial Strategy and Business Development")
- [  27 jul 2026 Minería y metalurgia  
    
     
    
     Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo 
    
     
    
     
    
    
    - ![Geraldine Cosset](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/206707/Geraldine-Cosset.webp)
    - ![Jared Purdy](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/212424/Jared-Purdy.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/las-decisiones-sobre-relaves-definen-desempeno-mina-a-largo-plazo "Por qué las decisiones tempranas sobre relaves definen el desempeño de la mina a largo plazo")
- [  02 jul 2026 Minería y metalurgia  
    
     
    
     Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales 
    
     
    
     
    
    
    - ![Charles Blais](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211197/Charles-Blais.webp)
    - ![Juan Pablo Vergara](https://www.assets.bbaconsultants.com/bba-production-assets/production/images/avatars/_size_avatar/211266/Juan-Pablo-Vergara.webp)
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/perspectivas/python-una-herramienta-clave-para-analisis-datos-en-procesamiento-minerales "Python: Una herramienta clave para el análisis de datos en el procesamiento de minerales")
- [  02 jul 2026 
    
     Stéphanie Turbide appointed Office Director, Mont-Saint-Hilaire 
    
     
    
     
    
     
       
    
     
    
      ](https://www.bbaconsultants.com/es-cl/news/stephanie-turbide-appointed-office-director-mont-saint-hilaire "Stéphanie Turbide appointed Office Director, Mont-Saint-Hilaire")
 
 

       

 

 

   

 Veamos lo  
que podemos  
hacer juntos [ Póngase en contacto con nosotros    

 ](https://www.bbaconsultants.com/es-cl/p%C3%B3ngase-en-contacto-con-nosotros) 

 

   

 1. ## Our experts' solutions
    
    BBA’s engineers were tasked with designing and commissioning a facility that would meet all safety criteria while remaining cost-effective and environmentally responsible, two essential project targets
    
    Our experts faced many challenges: high ground resistivity, restricted or no access areas, wildlife, record snowfall and an iterative overnight design process.
    
    BBA’s rigorous approach to electrical design, project management and commissioning contributed directly to the project’s timely delivery. BBA had to plan site work in advance and tailor its designs to ensure minimal disturbance of sensitive areas. More specifically, we made a tremendous effort to minimize the width of cable trenches and ensure that wind turbine grounding grids would not encroach on environmentally restricted areas.
    
    As expected, many geographical issues—such as the presence of large boulders and a high water table—became evident during the trench-blasting and cable-laying phase. So, our team was forced to produce new construction designs in fewer than 24 hours to prevent costly delays and ensure phase completion. We later performed the commissioning in the winter, despite harsh climate conditions, to keep the project on schedule.
    
    Iterations were also needed to design the grounding grids for the two substations and 87 wind turbines. While granite bedrock is an excellent material for anchoring wind turbines, it is a poor electrical conductor and therefore complicates the grounding of structures.
    
    The result: the largest single-phase wind project in Ontario, as well as the largest First Nation wind partnership project in Canada. The wind farm is composed of two separate facilities, one on each side of an inlet that stretches from Lake Huron into Henvey Inlet Reserve No. 2.